03 Dec Bonny Train 6 ASI Project – Balance of Plant
November 2005 – ongoing
All works except 132 Network Integration Completed.
132 Network Integration works which is dependent on shutdown for tie-ins is expected to be Completed by May’11.
Client: Nigeria LNG Ltd.
In partnership with Parent Company ENTREPOSE Contracting
Engineering, Procurement and Construction of
- Instrument Air Unit
- Nitrogen Unit
- Amine Oxidizer Unit
- Condensate Stabilisation Unit
- 132 KV Network Integration